Is there a way to pull old project data from an inactive custom form into a new custom form if they share some of the same fields and/or calculated fields? Do projects need to be active or can they also be closed? Could fusion run a scenario irregardless of the project status?
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
Ah sorry, I missed that there were calculated fields, here's what I would do.
1. Create new form with all fields, except without calculated fields that overlap
2. Apply new form to projects that have old form
3. Remove old form from projects
4. Add calculated fields to new form, and trigger recalculate
Views
Replies
Total Likes
If you apply your new custom form before you remove your old custom form, any fields that exist on both forms will have the data preserved.
Views
Replies
Total Likes
Thanks for your response, I tried that and received an error "You can't add Calculated Field to the same object in different expressions"
Views
Replies
Total Likes
Ah sorry, I missed that there were calculated fields, here's what I would do.
1. Create new form with all fields, except without calculated fields that overlap
2. Apply new form to projects that have old form
3. Remove old form from projects
4. Add calculated fields to new form, and trigger recalculate