Hi Laura, In your view definition, I suspect all you need to do is turn on the Min and Min on Planned Start Date and Planned Completion Date, respectively, to then have the minimum and maximum then "roll up" to the blue Master Project Creative Number (blue) grouping line, at the top of each of those columns. Regards, Doug
Doug Den Hoed - AtAppStore