I'm attempting to rebuild templates that I created within my sandbox environment but when I build them in prod the total project duration is completely off. I've included a screenshot below of the template I'm trying to recreate.
As you can see the development & review summary task says the steps will take 60 days in the sandbox but the same template with all the same tasks, durations, task constraints, and predecessors is saying it will take 112 days in production.
Would love to know if anyone has seen issues like this before! I've submitted a support ticket but they haven't responded to any of my emails : P. I'll close this question and include the solution if support is able to figure out what is going on before we can!
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
Circling back to confirm that I did try recalculating the template timeline. I tried working with support and hopped on a call with them to help them troubleshoot but they don't know what's causing the issue after a month of troubleshooting so it appears this is a bug without any solution
Views
Replies
Total Likes
Can you post a screenshot of a view that includes the task constraint, start day, and completion day as well, please.
Views
Replies
Total Likes
Hi @skyehansen, here's a screenshot with those columns!
Looks like the issue may be with tasks 13 &14 as they are set to as late as possible but not connected by predecessors to the go live which needs to finish at a set time. Regardless though, I'm still confused by why the dates are so different for both.
Views
Replies
Total Likes
It's difficult to comment accurately on how anything might have happened, since I was not there to witness the actions that led to this point. I think you mentioned that you were talking to Support about this so this is definitely a conversation you can take up with them. Suffice it to say that the reason that Workfront suggests that you make edits to your template by editing a project instead, and then reconvert it back into a template is to avoid issues like this. (They're much easier to spot in project form)
For the purpose of fixing your template, I would probably suggest that you try and see if you can change the start and complete day columns through inline editing.
I have recreated the templates from scratch and gotten the timing closer to what I was expecting to see. I'm just still unsure of what is causing the project to complete in twice the time when I put the same template from our sandbox into prod. I would think the project would calculate back from the final task's due date which was my intention but it's adding 60 days to the project that I can't remove even when I edit the start and complete day columns.
Either way, I'll try to work through this with support if they can find the time to respond to my emails. Thanks for your help here, was great to at least get some eyes on this so I know I wasn't missing something simple!
no worries and good luck with Support. The only other thing I can suggest would be to recalculate the template timeline if you haven't already done this.
Views
Replies
Total Likes
Circling back to confirm that I did try recalculating the template timeline. I tried working with support and hopped on a call with them to help them troubleshoot but they don't know what's causing the issue after a month of troubleshooting so it appears this is a bug without any solution
Views
Replies
Total Likes
Sorry, it's difficult for me to suggest more without knowing what's been troubleshot. It looks like 3 dates are not lining up? I am wondering if you have maybe tried toggling those three task constraints to ASAP and then back to ALAP? Also wondering if you have tried editing the completion days on all three?
Views
Replies
Total Likes
Views
Likes
Replies