So, we use Workfront projects to track delivery of service. Our standard schedule for a project is 9 months, our templates are set with planned durations that reflect that. As work progresses, we update planned dates, which makes the overall timeline longer or shorter. Is there a way to indicate if a project is ahead or behind where it should be in it's standard 9 month duration as work progresses?
We do currently take a baseline snapshot at the beginning of a project to capture the dates of the original 9 month duration. And we have Milestones set as well.
And I created a report to track current days in process (Date Diff (today, planned start))
Ideally, we'd like to see what percent of projects are on time (going as planned on our 9 mo timeline), at risk (a certain threshold behind where they should be at any point in process), or late (very behind and/or already over the 9 month duration).
Thanks!