I know I have this view/report somewhere ... I believe is was a LEAP takeaway from 2018 or 19....column that shows "last update" verbiage...for the life of me I can't find it. guess I need to use the "clean-up" dash.help? | Community
Skip to main content
Level 6
October 8, 2020
Question

I know I have this view/report somewhere ... I believe is was a LEAP takeaway from 2018 or 19....column that shows "last update" verbiage...for the life of me I can't find it. guess I need to use the "clean-up" dash.help?

  • October 8, 2020
  • 2 replies
  • 1419 views
No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Level 10
October 8, 2020
Hi Tegwyn, The WFPro “Last Note Summary” text might be what you’re looking for at: https://wf-pro.com/home/training/text-mode-examples/ Thanks, Narayan
TegwynSt1Author
Level 6
October 8, 2020

thank you! 😊

I've never seen this link before ....I'm thinking it was from "top 15 tricks" session, but this doesn't look familiar. I'll try it!

was not able to get a column that displayed last task name completed - all I can get is predecessor number to show. I submitted ticket but guess it's not possible.

think if i can have current task name to show that I could get that one...

TegwynSt1Author
Level 6
October 8, 2020

HOLY COW!!! that totally worked!!!!!!!!

kinda telling that I'm so excited by this LOL

YAY ---TY 👊

Level 10
October 8, 2020

I've added this example to the WFPro Text Mode Examples as well.