Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!
SOLVED

How to reset the "Due On" date for individual tasks to auto-update based on predecessor?

Avatar

Level 2

What I'm looking for is a way to reset the "Due On" field to auto-update based on the predecessor that's been assigned.

 

Let's say you set up a project and set all the predecessors, but the date on several tasks are manually changed for any reason. Once you manually edit a "Due On" date, it won't auto-update no matter what predecessors are assigned anymore. 

Is there a way to reset it back to auto-updating? Screenshot with notes attached to help clarify what I'm looking for.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 10

Ahh, yes. If you want step 14 to begin as soon as step 13 is done, change the constraint to "As Soon As Possible" to see if that updates your date. 

 

View solution in original post

8 Replies

Avatar

Level 10

Hi! What is your task constraint set to for step 14 in your example?

Avatar

Level 2

I'm not sure what you mean by constraint.

Also, I should maybe have mentioned I'm just a normal user in WF and only have certain permissions. I can create tasks and edit them and dates and such, but have no real admin capabilities.

Avatar

Level 10

Here is the support article for an overview on task constraints: https://experienceleague.adobe.com/docs/workfront/using/manage-work/tasks/task-constraints/task-cons...

 

For our projects, we use predecessors and we typically have our Task Constraint set to "As Soon As Possible" so the next task in line begins as soon as the previous step is complete. When we make a change to a task and have this constraint, the steps will update without someone having to manually changing the due date.

 

Can you check the task to see if you can see the task constraint that is set by clicking into that task and going to task details?

 

Screenshot 2023-09-29 at 11.26.57 AM.png

 

If you cannot see the constraint, I would check with your Admin to see what the constraint is for the project and ask how they set up the template (assuming this project is using a template).

Avatar

Level 10

Also, if you are unable to update the View for projects to pull in a column for Task Constraint, I would ask your Admin to add this in as well to save you the extra clicks to see how that tasks are set up.

 

Screenshot 2023-09-29 at 11.31.06 AM.png

Avatar

Level 2

Ok, so the constraint is set to Must Finish On. It does look like I might be able to edit that field if changing it would help?

Avatar

Correct answer by
Level 10

Ahh, yes. If you want step 14 to begin as soon as step 13 is done, change the constraint to "As Soon As Possible" to see if that updates your date.