How do you mark a task done (100%) using the mobile app? | Community
Skip to main content
Level 2
December 30, 2020
Question

How do you mark a task done (100%) using the mobile app?

  • December 30, 2020
  • 1 reply
  • 749 views
No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

SamanthaIsin
Level 7
December 30, 2020

When you are on the home page on the app you can see a list of tasks. On any one of those you can slide to the left and you'll get three options. 1) Update 2) Move to Requests and 3) Done. Selecting Done will by default set to the task to 100% complete.

OR

You can open the task and press the plus button to make a new update. Click the slide icon on the bottom left of the update and you'll have the option to change statuses, conditions, commit dates, and percent complete.

OR

You can open the task and select the details. Then mark the task as done.

CarrieDoAuthor
Level 2
December 30, 2020

Thank you