I recently had another planner delete a project and the default for the project hours was set to the default to keep the hours on each person's timesheets under General Hours. Now these hours no longer roll up into a project. How can I get them back onto the recently restored project so that those hours show up on our reporting.
Views
Replies
Sign in to like this content
Total Likes
Depending on what is selected in Setup > Timesheets & Hours > Preferences determines how the hours are restored (more information here). The section, Project, Task or Issue Deletion Preferences, offers two options:
As for the project that was already deleted and restored, those hours will stay under the General area of the timesheets. You can re-log the hours on the Project, however, that will require a little bit of manual work.