Hello All,
I have a situation where I set a task to 100% complete. This normally removes it from assigned users' timesheets. However, if a user pinned the task on their timesheet, it remains on their timesheet and they can still log hours on the task even when it is set to complete.
How can I, as the owner of a project, “close” a task to ensure that users can no longer add hours to it?
Topics help categorize Community content and increase your ability to discover relevant content.
Sadly, you can't. We tried to get this sorted out with support but had no luck. Since there is no createDate on the hour object (it is misused for the entry date), you cannot even report on any hours added after the task had been closed.
Views
Replies
Total Likes
I submitted it as an idea in the innovation lab. Please vote for it via the link below so it can get some traction:
Views
Replies
Total Likes
Done :-)
Views
Replies
Total Likes
Hi Joe,
I agree with Chris; although I hadn’t thought about his point on the Entry Date blurring the lines further: ouch.
While you're waiting for Joe's idea to work its way up the Innovation Lab leader board, I can offer a couple of suggestions:
Regards,
Doug