We have recently started using workfront for all our employees/projects.
When they start a task - moving the percentage complete past 0% this does capture the date and time. Along with when they mark it 100%.
Does this track the hours on the project? Or is the only way to capture hours is by having them manually logged to the task or timesheet?
Thank you!
Solved! Go to Solution.
Views
Replies
Total Likes
The only way to to capture hours is by having them manually log hours to the task or timesheet.
Start and completion may not accurately reflect actual time worked on a task such as when a user needs to pass their work to someone else for review before marking their task complete or something along those lines.
Views
Replies
Total Likes
The only way to to capture hours is by having them manually log hours to the task or timesheet.
Start and completion may not accurately reflect actual time worked on a task such as when a user needs to pass their work to someone else for review before marking their task complete or something along those lines.
Views
Replies
Total Likes
Thank you for the reply!
Views
Replies
Total Likes
Views
Likes
Replies