Hours tracking based on updates to percentage complete column | Community
Skip to main content
Level 2
February 13, 2023
Solved

Hours tracking based on updates to percentage complete column

  • February 13, 2023
  • 1 reply
  • 587 views

We have recently started using workfront for all our employees/projects. 

When they start a task - moving the percentage complete past 0% this does capture the date and time. Along with when they mark it 100%. 

 

Does this track the hours on the project? Or is the only way to capture hours is by having them manually logged to the task or timesheet?

 

Thank you! 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Heather_Kulbacki

The only way to to capture hours is by having them manually log hours to the task or timesheet.

 

Start and completion may not accurately reflect actual time worked on a task such as when a user needs to pass their work to someone else for review before marking their task complete or something along those lines.

1 reply

Heather_Kulbacki
Community Advisor
Heather_KulbackiCommunity AdvisorAccepted solution
Community Advisor
February 14, 2023

The only way to to capture hours is by having them manually log hours to the task or timesheet.

 

Start and completion may not accurately reflect actual time worked on a task such as when a user needs to pass their work to someone else for review before marking their task complete or something along those lines.

EMTFSAuthor
Level 2
February 14, 2023

Thank you for the reply!