Expand my Community achievements bar.

The next phase for Workfront Community ideas is coming soon. Learn all about it in our blog!
SOLVED

Having trouble deciphering Predecessor rules: need help!

Avatar

Level 3

The use case:

The business would like a task to be able to be marked as "In Progress" even if the predecessors are not fully completed, but don't want the task to be able to be completed before the predecessors are complete.

It looks like either Finish-Finish (ff) or Scheduled-Start (sd) should work, but I am still unable to prevent the task from not completing. It's more than likely I am misunderstanding the rules, but I have tried every single predecessor type and cannot prevent the task from completing before its predecessor is complete.

In the case below: I'd like either task 2 or 3 to be able to be moved into In progress, but not able to be completed until Task 1 is marked as complete. What should go in the predecessor columns?

Thanks in advance,

Ryan

order.JPG

1 Accepted Solution

Avatar

Correct answer by
Level 3

Hi Ryan,

 

I think you're looking for ffe - Finish to Finish Enforced. More info here: https://experienceleague.adobe.com/docs/workfront/using/manage-work/tasks/use-task-predecessors/enfo...

Using that as the dependency type on tasks 2 and 3 should get you what you're looking for. 

 

-John 

View solution in original post

1 Reply

Avatar

Correct answer by
Level 3

Hi Ryan,

 

I think you're looking for ffe - Finish to Finish Enforced. More info here: https://experienceleague.adobe.com/docs/workfront/using/manage-work/tasks/use-task-predecessors/enfo...

Using that as the dependency type on tasks 2 and 3 should get you what you're looking for. 

 

-John