Hi Marshall, If I'm following, you're on the right track; but since you're seeing blank information in your view, I'd suggest you confirm that the formula you put on the DE:Duration from Ready to Start to Completion custom parameter is calculating as expected, and is present on all the Tasks you care to examine in this manner. As for other ideas...although it's rarely discussed in this community forum, Workfront has a concept called "https://support.workfront.com/hc/en-us/articles/217182397-Understanding-the-Projected-Completion-Date-for-Projects-Tasks-and-Issues">Projected Dates that I encourage you to read about and consider leveraging in such "how are things going vs my plan" cases. "https://support.workfront.com/hc/en-us/articles/216674618-Creating-Baselines">Baselines might be an option, too, if you're a (moving) line-in-the-sand fan; and they can even be "http://store.atappstore.com/product/create-baselines/">automated . Regards, Doug Doug Den Hoed - AtAppStore Got Skills? Lend a hand!