Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!

Create Task report that shows next first open task if the previous task was completed with 100%

Avatar

Level 1

Can anyone help me to know how to create task report that shows next first open task if the previous task was completed with 100%

4 Replies

Avatar

Level 3

It sounds like this may be a good starting point for the filters in your task report:

  • Task >> Can Start Equal True
  • Task >> Is Complete Equal False

Is there more that you want to see?

Avatar

Level 1

Thanks for sharing.

Yes, we want to show only one task per project that is only when previous task should be completed with 100% and then we should show next task (one task per project).

Avatar

Level 3

If your workflow is pretty linear and you don't have multiple tasks with the same predecessor, I think those filters might do the trick.

Avatar

Level 1

Great! I have got similar to what we want. Thanks for you help.