Is it possible to copy a group of tasks in a project to another project without copying the comments? We have several yearly large projects that require the same long lists of tasks and we want to copy the tasks over but not include any of the previous information (i.e. custom forms, documents, comments). We can see how to remove documents, but not comments. Ashley Thomas
Hi Ashley, One approach is to save the Project as a Template ("bye-bye comments..."), cull any unwanted tasks (to only the group of tasks you need), and then on the target Project, insert (that) Template. Regards, Doug Doug Den Hoed - AtAppStore