Consistent Planned Start and Completion Dates Across Time Zones

Avatar

Level 1

I work with teammates across the globe. We've noticed that our planned start and completion dates will vary depending on the time zone. For instance, if I enter a campaign for 11/6 while in the Eastern time zone, my colleague who is in the Central time zone will see it as 11/5.  Is there anyway to set Workfront so that we all see the same date?

1 Reply

Avatar

Level 4

Hi @ToniC_605 , 

 

We faced a similar issue. Workfront dynamically selects the timezone as per the user's system clock. To get around this limitation, you can either change the timezone for your colleague on both their profile and their system. Or create a report that converts the dates to a specific timezone (using text mode). There are also some helpful tips on using schedules here - https://experienceleague.adobe.com/en/docs/workfront/using/basics/tips-tricks-for-basics/working-acr...