I work with teammates across the globe. We've noticed that our planned start and completion dates will vary depending on the time zone. For instance, if I enter a campaign for 11/6 while in the Eastern time zone, my colleague who is in the Central time zone will see it as 11/5.  Is there anyway to set Workfront so that we all see the same date?

1 Accepted Solution

Avatar

Correct answer by
Level 6

Hi @ToniC_605 , 

 

We faced a similar issue. Workfront dynamically selects the timezone as per the user's system clock. To get around this limitation, you can either change the timezone for your colleague on both their profile and their system. Or create a report that converts the dates to a specific timezone (using text mode). There are also some helpful tips on using schedules here - https://experienceleague.adobe.com/en/docs/workfront/using/basics/tips-tricks-for-basics/working-acr...

View solution in original post

2 Replies

Avatar

Correct answer by
Level 6

Hi @ToniC_605 , 

 

We faced a similar issue. Workfront dynamically selects the timezone as per the user's system clock. To get around this limitation, you can either change the timezone for your colleague on both their profile and their system. Or create a report that converts the dates to a specific timezone (using text mode). There are also some helpful tips on using schedules here - https://experienceleague.adobe.com/en/docs/workfront/using/basics/tips-tricks-for-basics/working-acr...

Avatar

Administrator

@ToniC_605 Just checking in — were you able to resolve your issue?
We’d love to hear how things worked out. If the suggestions above helped, marking a response as correct can guide others with similar questions. And if you found another solution, feel free to share it — your insights could really benefit the community. Thanks again for being part of the conversation!