Hi @Heather Kulbacki‚ - this is exactly what I'm looking for but for the life of me can't follow along to understand how to build it and report on it - do you happen to have screenshots that you could send?
Views
Replies
Total Likes
Hi Laura,
Here's a screenshot of our fields. A couple points to remember in creating these fields
Then the last field "Creative Cycle Time" is just a calculation between "Creative Execution Start Date" and "Business Review Start Date" and that "Creative Cycle Time" field can be pulled into a report.
Additionally, we originally came up with this workaround because a user would click "Work on It" on a task or issue, but would have to manually change the task/issue status to capture an actual start date. And we didn't want them to have to do that extra step.
I suspect we'll be retiring this form soon. Now that we have the ability to re-set the "Work on It" button to a "Start Task" or "Start Issue" button within each Team, we're reminding users to click "Start Task/Issue" when they actually start working on something to track the cycle time.
Thank you so much Heather :)