Can Issues be added on a Task Level in a Project Template?

Avatar

Level 2

We leverage Issues to add specific information that may apply to our deliverables per our retention policy (like expiration dates). These can be missed on the Project level, and I was wondering if we could use the Complete - Pending Issues status as a flag that there is an extra action on the corresponding task. Since these are added for specific requests, we are looking to add them to a Project Template so they populate automatically. Thanks! 

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 4

I think you can't add issues to a template (either on the project or on the task level). I guess because the idea is that issues capture unplanned work. (Happy to be challenged, though, if someone knows a way.)

If you insist on having issues added automatically to your projects, maybe explore options such as custom form data added to the template tasks, which triggers a Fusion scenario upon project creation that adds the issue to the project task.

Avatar

Level 2

Thanks for your response! This was my initial thought, but I was curious if there was an opportunity to do it without a Fusion Scenario. Our instance leverages Issues (with custom forms) for procurement as our main usage, the unplanned nature isn't inherent.