“Assign Design” is often the first task on a project.
We would like to set the default end date of all Assign Design tasks to a day of the week (Tuesday).
Is it possible to add a lag type to the first task of a project, utilizing “3w” somehow?
We would prefer to achieve this without having to add a task prior to “assign design”
If it’s not possible, I think we’ll have to ask our PM’s to manually set the duration to make that task end on a Tuesday each time they create a project.
Hi @CathyKe1,
I suspect (valid) resistance from PMs instructed to manually adjust a certain task to always end on a Tuesday (particularly if your plans then shift enough to negate that change), so instead, invite you to (buckle up and) consider:
By doing so, if I'm imagining correctly, and assuming the task in question is <1 day in duration (trickier otherwise), Workfront will recognize the Tuesday Bot for that task as the primary assignee, and then look to it's schedule (Tuesdays Only) to schedule the work, and as a result, automatically "bump" the planned date to the first available Tuesday...even when your plans change, with no extra work on behalf of the PMs.
Regards,
Doug
cc: note to self @Doug_Den_Hoed__AtAppStore
Thanks for this interesting suggestion, @Doug_Den_Hoed__AtAppStore . I finally have a little time to get my head around it.
A few follow-up questions to the points you laid out above:
Any idea what I'm doing wrong here?