Expand my Community achievements bar.

The Community Ideas review for H1 2025 is out now, see which ideas our Product team prioritized and let us know your thoughts.

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

Calculated Custom Field Help - How to show variance between Planned Completion and Actual Complete Date

Avatar

Level 2
Hi All, Look for any suggestions. I would like to create a calculated custom field showing the variance (days late or days ahead) of project planned completion date vs actual completion date. I have tried created a custom field using this formula: SUB(Actual Completion Date,Planned Completion Date) and adding the custom form to the projects in question. I added the column to the report view but I cannot get the calculation to formulate. Any ideas on what I am doing wrong or how to get this report to work? Eric Roybal Director, Project Management One & All
1 Reply

Avatar

Level 2
found it: For the difference between Planned Date and Actual Completion Date, the formula would look like this. WEEKDAYDIFF( Planned Completion Date,Actual Completion Date ) Eric Roybal Director, Project Management One & All