At the program level, when I am looking at a list of the active projects, how do I create a column that pulls in the current task on each project into a custom view?

Avatar

Level 2
 
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 10

Hi Jeremy,

Here's one way, from an example at wf-pro.com:

displayname=Current Task

listdelimiter=

listmethod=nested(tasks).lists

textmode=true

type=iterate

valueexpression=IF({numberOfChildren}=0,IF({canStart},IF(CONTAINS("CPL",{status}),"",CONCAT({name}," "))))

valueformat=HTML

Regards,

Doug