Hi Lindsay, It's a known behaviour in Workfront that your waterfall project task dates will be overwritten with the iteration date. Workfront prioritizes the iteration date over any manually specified date in a project task list. Recently, Workfront launched Kanban support. This gets around this issue since there are no iterations, but if your team is already working in Scrum, this would obviously require a process shift. "https://support.workfront.com/hc/en-us/community/posts/115006885108-Adjusting-planned-dates-in-an-iteration" Here is an idea in the Idea Exchange you can vote for if you want to work in Scrum but still want the ability to overwrite iteration dates. Barbara Sedlack BMO Financial Group