Hi Tegwyn, Am following this also, as I am interested in how to combine the 2... I'm not totally sure I follow, but it sounds like 2 templates on the one converted project? If that's the case, you gave me the idea that one way this could work, is using -
https://experience.workfront.com/s/article/Understanding-Cross-Project-Predecessors-638211475 maybe even combine with the 'enforced' predecessors, if there was little flexibility in the project timelines (?) - that way you could have 2 different schedules on each project - however, this won't make one 'trump' the other - just be reliant on the other, possibly...although, not tested and not used these yet... Just an idea....but, would be great to hear back from the community on this, for sure... Miranda Rais GVC