SOLVED

Actual Hours in the Workload Balancer

Avatar

Level 1

Are you able to include/view actual hours in the workload balancer? If yes, can someone please tell me how?


Thanks,
Brenda

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi Brenda,

 

You cannot view actual hours in the Workload Balancer, only planned hours.

 

You would need to use the Resource Planner to be able to see planned vs actual hours.

 

Best Regards,

Rich. 

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

Hi Brenda,

 

You cannot view actual hours in the Workload Balancer, only planned hours.

 

You would need to use the Resource Planner to be able to see planned vs actual hours.

 

Best Regards,

Rich.