Task status updates when time is entered

Avatar

Level 4

5/3/17

If a user logs hours against a task that hasn't started, we'd like the system to automatically update the task status to In Progress.

5 Comments

Avatar

Level 2

5/10/17

Agreed. Our users are required to track time so always remember to do that but forget to mark tasks in progress. This ultimately makes the actual start date behind the planned start date and then Workfront thinks your task is at risk or in trouble.