Need to have a option to limit project "manage right" for "Resource Manager".
All we need resource managers to do is assign resources and use the tool to monitor resource load. We trained them to use the new people /scheduling area. This will be very helpful for our company if more options/filters can be given(different idea exchange post)
The major issue for us is that they are also given right to change project "name"; "planned date", etc if they are assigned to resource owner. During our testing, our resource managers did "accidentally" changed the predecessor/ due date/ project name etc and "NO" notification to project owner can be set up either.
This can be a controlling nightmare for us as PM should be the only persons should grant the right to update these field in our company.
We also checked with workfront consultant". There is "NO" work around. So, if we remove them as resource owner, then the new resource planning tool become useless to us.
Please correct this
Thank you