Currently, a dependent tasks shows as ready to start when the predecessor is "Complete - Pending Approval". We need the ability to have dependent tasks not show as ready to start until the preceding task is approved and therefore truly complete.
This seems so obvious that my users assumed that was how it already works - as a result we had incomplete/inaccurate items sent out (because the "send item" task said canstart=yes) when the predecessor task was complete-pending approval. I agree & think this idea should also be expanded so that a dependent task does NOT show as "Can start = True" when the predecessor task has the status "Complete - Pending Issues".