Dependent tasks wait for approval

Avatar

Level 7

3/10/17

If a dependent task has a predecessor that is pending approval then it should not be ready to start.

3 Comments

Avatar

3/10/17

Brian, for this predecessor pending approval scenario, could you enforce the predecessor relationship to prevent the successor from starting (assuming it works that way, and assuming it working that way works for you)?

Regards,

Doug