I've seen this on a small scale where you have tasks included in the project that have the duration and planned hours set at 0.
Are the remaining tasks set for 0 duration and/or 0 planned hours...? if so, I think that might cause the system to "calculate" that it is 100% done.
My company doesn't set duration or planned hours, so I didn't even notice that they were auto filling 0 instead of 1. Updating this worked! Thanks.
I've seen this on a small scale where you have tasks included in the project that have the duration and planned hours set at 0.
This is still happening to me - I have looked into all the projects and the tasks all have a value on. What am I missing?