Projects Incorrectly Showing 100%

Avatar

Level 3

Has anyone else had issues with projects incorrectly showing a progress of 100%? When you open the project, there are tasks at 0%, but the overall project still is auto-calculating to 100%. 

Any ideas on the cause or a solve? 

1 Accepted Solution

Avatar

Correct answer by
Level 1

I've seen this on a small scale where you have tasks included in the project that have the duration and planned hours set at 0.

View solution in original post

4 Replies

Avatar

Level 2

Are the remaining tasks set for 0 duration and/or 0 planned hours...? if so, I think that might cause the system to "calculate" that it is 100% done.

Avatar

Level 3

My company doesn't set duration or planned hours, so I didn't even notice that they were auto filling 0 instead of 1. Updating this worked! Thanks. 

Avatar

Correct answer by
Level 1

I've seen this on a small scale where you have tasks included in the project that have the duration and planned hours set at 0.

Avatar

Level 5

This is still happening to me - I have looked into all the projects and the tasks all have a value on. What am I missing?