That sounds like a great work around. I've created the last week, 2 weeks ago, 3 weeks ago, and 4 weeks ago custom date ranges. I'll let you know Monday if this solution works.Thanks urs.boller
urs.boller Yes, the date is based on a rolling timeframe. When you say you used the week dimension on the left side you mean you dropped it into the rows? I am using it as a column. I've already checked with client care and they stated that this is a design flaw."What happens is if you drop a dime...
Hello,I built a table that uses the "Week" dimension in the "X axis" but it doesn't automatically updated when you use a rolling week date range.It currently requires you to manually remove the "week" dimension column and apply it again to reflect the new week.This defeats the purpose of scheduling ...