Do I have to change a setting? Here is a task with 1-day duration calculating planned cost using the planned time of 1 hour x a user's cost per hour. Here is the exact same task when I switch to a 0 day duration, planned cost updates to $0. this all rolls up to the project cost, creating incorrect ...