Hi Frank, For incomplete tasks, we first discuss as a team why the scope was not delivered and then we split the task by adding a part 2, 3, 4 etc directly on the current iteration storyboard. We set the former as complete, if we delivered part of the scope, and leave the part 2 task in the new colu...