Hi, I am hoping someone can help. I am working with WorkFront planning in work for our design team. If we have a task that spans over 5 days (Monday - Friday) with 10 planned hours I can allocate hours per day. i.e. 5 hours Monday - 5 hours Friday in the scheduling tab. If I then adjust any dates in...