  • I have a task that was planned for 76 hours, but was completed in 31. I have updated the % Complete to '100%'. Workfront is telling me that I still have 45 hours remaining on the task. I have not been able to find a way to zero-out the 45 hours. Can anyone tell me how to reduce the Hours Remaining t...

    Type

    Questions

    Views

    282

    Likes

    0

    Replies

    3
  • Greg, The tips from you and Lucas are appreciated and are effectively the same. What I am trying to do is track the actual hours spent on tasks so that I can work with the development team to understand how well we are estimating our work. So, I definitely care about the hours at a task level. I...

    Type

    Questions

    Views

    263

    Likes

    0

    Replies

    0
  • I have a project that is new to WF, but has been underway for a few months. I have created the project, the tasks, entered the data for the planned hours, etc. There are a few tasks that already have actual hours and I need to be able to record these hours in WF. I am accustomed to how to do this in...

    Type

    Questions

    Views

    263

    Likes

    0

    Replies

    3