Thanks so much for responding. Unfortunately - it doesn't seem to like the format statement. Each time I try to add valueformat=compound#M:D The system erases it. displayname=Duration in Weeks durationunitfield=durationUnit.value linkedname=direct namekey=duration querysort=durationMinutes textmode=...
Hi, I created a calculated column to calculate the number of days between Planned Completion and Planned Start. Is there anyway to format the result in number of weeks as opposed to number of days. Michele Banks Christus Health