hi Sarah, there's not a way to force a view on someone, especially not as a default. If you have system admin access, you can log in as that user, and change the view for them, but that's about it. And I don't know whether that view stays or whether it reverts back to standard when they reset the us...
hi Jernae, the workfront article for creating calendars is here https://experience.workfront.com/s/article/Creating-and-Managing-Calendar-Reports-1669195290 -- it doesn't make it clear enough, but basically you can only add dates to the calendar that have to do with the planned, projected, and actua...
hi Vicki, your formula works--at least, it works in my system on a task if the calculated field is on a task custom form on that task. What is it that isn't working on your end? Also I suggest you try some troubleshooting. What's your custom form field on, and did you click the tiny checkbox that sa...
I'd support adding a fourth. I think it's silly that you can't put tasks on hold. Projects and issues can go on hold but tasks can't? Seems like oversight. Additionally I'd like more "status equates with" reporting options (feels like right now "Project Status Equates With" is the only one I get to ...
We have the same problem, and while we've managed to deal with it as best we can in Classic, I feel like the new Experience UI is going to make the problem worse as the fields are even more spread out. My director has already mentioned he will need to reformat the custom form again to account for it...
Not really sure what kind of report you are in (is it a task report?) but I was able to get the following to show up on a project report. displayname=Event Name linkedname=direct namekey=name querysort=name textmode=true valueexpression=IF({DE:yourfieldname}="answer",CONCAT({name}),"") valueformat=H...
ah, that's a tough one since Workfront calendars do not currently operate off custom fields. You're specifically looking to tie it into the planned completion date of a project, task or issue. It's fair and not unusual for most project planned completion dates to go past the launch date, but that me...
Open issues, tasks and projects are the least of our worries. The footprint of a user can expand to objects they own and share with other users whose access can be impacted by deactivation. For example, deactivating a user will render their shared calendars unusable. In addition, the meaning of "aut...
Is there a task in that project that indicates the launch date? if so -- and if you only need that launch date -- I would suggest that these tasks are either named in a specific way or somehow identified in the system. You can then use a custom name that is the name of the project that the task is i...
hi Nick, have you tried the solution discussed in this link? (summary: use AND:1:___ code) "https://community.workfront.com/discussions/community-home/digestviewer/viewthread?MessageKey=19dc2709-eb70-4fb3-83cb-dee478e686ae&CommunityKey=ccf3381b-a473-4ef2-9f81-4dd3244cf522&tab=digestviewer#bm19dc2709...