This may or not be helpful, but I created a custom report that shows all of the users on my team (grouped by: assigned to), project name task name, the % complete on each, and how many days past the due date (if applicable) each task is. I know it's not as quick to get to as workload balancer, but you can add and remove as much detail you want from creating a custom report.
Columns- Can Start, Project Name, Task Name, Assignments, Duration, Pln Hours, Start On, Due On, % Complete, Days Late