Work-Rquest Approval ...

Avatar

Level 2
Hello All, I am new to WF... We have established an approval process for all work-request submitted. However, how do we prevent a PM from using a NON-APPROVED work-request to stand a project up? Thanks, Tien Nguyen Humana - Care Plus Health Plans
1 Reply

Avatar

Level 10
Could you set the Approval Process to change the Status to Dead when the Approval is rejected, then have the setting in your Setup (under Projects > Life After Death) and uncheck the boxes so the project can't be changed. Would that work? Vic Alejandro, PMP, CSM | IT Program Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/"> http://www.denverwater.org INTEGRITY | VISION | PASSION | EXCELLENCE | RESPECT