I have a task (Design/Build/Test) in a project that says that it is waiting on another completed task (Concept). It says this on the Updates tab of the Design/Build/Test task. Concept task is at 100%, and so is Design/Build/Test task. So why is Design/Build/Test waiting on Concept? Any help would be appreciated. See uploaded screenshots. Dave Rulon Great Dane Savannah, GA 912-644-2452