Hi Team,
Can anyone help me, what would the calculation be for variance in weekdays between baseline Task planned start date and task planned start date?
Hello Namratha,
although I did not work with Baselines yet, according to the API-Explorer this should help:
WEEKDAYDIFF({defaultBaselineTask}.{plannedStartDate},{plannedStartDate})
Regards
Lars
Very sorry for the late reply. This works well! Thank you so much.