Level 1
Level 2
Sign in to Community
Learn more
Sign in to view all badges
Expand my Community achievements bar.
Hi Team,
Can anyone help me, what would the calculation be for variance in weekdays between baseline Task planned start date and task planned start date?
Hello Namratha,
although I did not work with Baselines yet, according to the API-Explorer this should help:
WEEKDAYDIFF({defaultBaselineTask}.{plannedStartDate},{plannedStartDate})
Regards
Lars
Very sorry for the late reply. This works well! Thank you so much.
Views
Likes
Replies
Like