Variance calculation

Avatar

Level 2

Hi Team, 

 

Can anyone help me, what would the calculation be for  variance in weekdays between baseline Task planned start date and task planned start date?

2 Replies

Avatar

Level 10

Hello Namratha,

 

although I did not work with Baselines yet, according to the API-Explorer this should help:

 

WEEKDAYDIFF({defaultBaselineTask}.{plannedStartDate},{plannedStartDate})

 

Regards

Lars

Avatar

Level 2

Very sorry for the late reply. This works well! Thank you so much.