Unaccepted tasks show up in Working On tab

Avatar

Level 2
As we've been building out our projects, I've had dozens of tasks show up in my Working On tab, when I've never clicked Work On It. Why is this and how can we change it? Multiple times I've had to go through my entire task list and click Send Back to Work Requests to de-clutter my page. I think this happens when we change the status of a project to On Hold, then make it Current again, or something like that. I've seen this happen before with projects I've built myself, but now another team member is making them and my page keeps filling up again. Help is appreciated. Thanks! Kenny George
2 Replies

Avatar

Level 10
There is a setting on your own account, my settings. If you tick off the box that " all new tasks you've put on projects will automatically go to your Working On tab. Polly Co

Avatar

Level 2
Thanks! I just unchecked that box and we'll see what happens. Kenny George