Expand my Community achievements bar.

The next phase for Workfront Community ideas is coming soon. Learn all about it in our blog!

Tracking Mode- User Must Update

Avatar

Level 6
Hi, Can anyone tell me when using the task tracking mode- User Must Update what criteria is used to determine the status. I get that if a task is not 100% and it's after the planned completion date it is Late. But what make it At-Risk? What makes it Behind? On-Track? Thanks! Mollie Mollie Shatek JLL
1 Reply

Avatar

Level 10
Is this what you're looking for? "https://support.workfront.com/hc/en-us/articles/216636328-Understanding-Progress-Status-of-Tasks">https://support.workfront.com/hc/en-us/articles/216636328-Understanding-Progress-Status-of-Tasks Vic Alejandro, PMP, CSM | IT | Sr. IT Project Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/"> http://www.denverwater.org INTEGRITY | VISION | PASSION | EXCELLENCE | RESPECT