Task/Issue/Iteration Report - When does a Task/Issue get added to the Iteration

Avatar

Level 2
A request from my team - We want to know how many Tasks/Issues are added to the iteration during the course of the iteration. Has someone cracked this nut? I'd like to understand how scope creeps in the iteration. We can see it on the burndown, but need the report to know which ones or a view, etc. Brady Robinder Comcast Corporation - West Division XOC
1 Reply

Avatar

Level 10