Does anyone know how to add the planned completion time to the homepage worklist for all users with a worker license?
Solved! Go to Solution.
Views
Replies
Total Likes
Hi Laura,
you can do this via layout template configuration and make sure this layout(s) are assigned to the right users.
Select "home and summary" and specify on which object types you want users to see Planned Completion Date, e.g. Task, Issues.
One more thing to watch out for, home area would distinguish between task/issue requests and task/issue working on
good luck!
Views
Replies
Total Likes
Hi Laura,
you can do this via layout template configuration and make sure this layout(s) are assigned to the right users.
Select "home and summary" and specify on which object types you want users to see Planned Completion Date, e.g. Task, Issues.
One more thing to watch out for, home area would distinguish between task/issue requests and task/issue working on
good luck!
Views
Replies
Total Likes
Thank you! I already have it set up exactly like that for both planners and workers BUT only the planner shows the time. Workers do not.
Views
Replies
Total Likes
ahh, I get now emphasis on "time".
if the field is there, but time is missing, please uncheck "hide timestamp" setting in the same area
Views
Replies
Total Likes
Did that too.
Views
Replies
Total Likes
I have done a side-by-side comparison of both templates and cannot figure out the difference!
Views
Replies
Total Likes
Views
Likes
Replies