Question: For the NEW resource tools, does the project level setting for Resource Leveling Mode [Automatic or Manual] apply? TIA! Rhonda Lindner Rhonda Lindner Collegis Education
I'd be interested in knowing this too. The help articles appear to be based only on the legacy tools, but I'm really not sure. Matt Marks Banner Engineering Corp.
Good question! I have consulting call with Workfront this afternoon on Resource Management. One of our questions is if we can keep leveling manual so that we can employ other mitigation strategies besides moving work out. I'll let you know what I find. Jean Chapdelaine Sr. Manager, Program Execution NovuHealth
So you can apply automatic or manual resource leveling at the project setting level with the new resource management functionality. Does that answer your question? Jean Chapdelaine Sr. Manager, Program Execution NovuHealth