Yep those are my usual tricks. I hoped I had missed something. On Sun, Feb 12, 2017, 5:19 PM ....Doug.... Den Hoed < reportingforum@communitylists.workfront.com> wrote: > Hi Melinda, > > Although it is available through the API (as you point out), I don't > believe that the Journal object is exposed through the Workfront reporting > engine (which hasn't changed in some time, whereas Journal is a relatively > recent addition). > > So, a few ideas: > > - you did the first one all ready, by trying turning on the Update > Feeds to "watch" the Project Planned Completion Date, and see if doing so > will record the data you need in the Notes object (which is > reportable)...but no go > - consider taking Baselines, then comparing the Baseline value against > the current value to detect the difference > - consider a calculated field that will detect the previous value (so > you can contrast when it changes), with a second input field that will let > you "force it" to the current value once the time comes > > Regards, > > Doug > > -----End Original Message----- >