Report on user\'s OOO?

Avatar

Level 6

Is it possible to report on OOO logged in Workfront so that project managers be alerted scheduling impact across all projects?  We're looking for a solution so PMs don't have to go into each project to find this info.

6 Replies

Avatar

Level 4

Creating a 'Time Off' report may help you:

_Manish_Singh_1-1668758677069.png

Avatar

Level 4

Another way to do it, aside from already suggested Time Off report, is Calendar that would pull in all Time Off info

Avatar

Level 4

Adding to the above, 'Calendar + Workload Balancer' would be a good combination to know scheduling impact.