Expand my Community achievements bar.

Report for hours in resourcing pool

Avatar

Level 1

Hello, I am trying to come up with a report from the resourcing pool. Have a chart of PLN vs ACT hours in Workfront. Anybody has an idea on which kind of project I should select and what is the process.

3 Replies

Avatar

Employee

Hi Davy - Comparing Planned and Actual hours is a little tricky. You can do it with tasks and projects (and then of course programs, portfolios, companies, and groups), but it gets harder when you are working with roles and users. 

 

The main reason is that the planned hours info is on the Assignment Object type while the actual hours are on the Hours object type. You can kind of get away with this if you only assign one user or role to every task, but most people have multiple people on at least a few tasks. 

Avatar

Level 1

is it possible to schedule a call to get help with that ?

 

Avatar

Level 10

Hi Davy, 

If your call is not too personal from company point of view, then if you allow. I would also like to join about the tips to create such report.

Have a nice day!

 

Best regards,

Kundan Kumar.